Home › Articles › Data centres and the grid: flexibility, curtailment and load shedding

Article

Data centres and the grid: flexibility, curtailment and load shedding

Updated · 15 min read

In short

Large data centres strain grids because they want a lot of power, in one place, quickly, while lines and power stations take years to build. Some AI work, such as training and batch jobs, can pause or move when the grid is stressed, and grid operators, regulators and some AI companies are starting to turn that into agreements, connection terms and emergency rules. Flexibility is useful but limited: interactive AI services still need power on demand.

Key points

  • The IEA estimates that around 20% of planned data centre projects could be at risk of delays unless grid risks are addressed.
  • Training, fine-tuning and batch jobs can often pause or move; interactive AI services that answer users in real time usually cannot.
  • A 2025 Duke University study estimated that 76 GW of new US load could be added if it accepted curtailment for 0.25% of its maximum uptime, rising to 98 GW at 0.5%.
  • Google said in March 2026 that it had built 1 GW of demand response capacity into long-term contracts with US utilities, by limiting or shifting machine learning work.
  • Texas (2025), Ireland (2025) and the EU (2024) have all written rules on curtailment, flexible connections or emergency demand reduction that can apply to data centres.
  • Carbon-aware scheduling (cleanest hours) and grid-aware scheduling (avoiding peaks and constraints) often agree but not always, so a scheduling policy should say which it follows.

A typical AI-focused data centre uses as much electricity as 100,000 households, and it wants that power within a few years. This article explains why that strains electricity grids, which AI work can bend to the grid's needs, and what operators, regulators and AI buyers are doing about it: demand response, flexible connections, curtailment and, when things go wrong, load shedding. For how much electricity data centres use overall, see AI and data centre electricity demand.

Why do large data centres matter to grids?

Because they are big, concentrated and fast to build, while grids are slow to expand. The International Energy Agency (IEA), the source of the 100,000-household comparison above, estimates that, unless grid risks are addressed, around 20% of planned data centre projects could be at risk of delays.

The IEA's 2025 Energy and AI report sets out why:

  • Long queues. Grid connection queues for both supply and demand projects, including data centres, are "long and complex".
  • Slow build. New transmission lines can take four to eight years in advanced economies, and wait times for transformers and cables have doubled in the past three years.
  • Clustering. Nearly half of US data centre capacity is in five regional clusters, and 50% of data centres under development in the US are in existing large clusters, so the strain is local.

Ireland shows what concentration looks like: the Central Statistics Office reports that data centres used 23% of the country's metered electricity in 2025. In Great Britain, Ofgem's April 2025 decision on connections reform found that 444 GW of new connection applications were made across transmission and distribution in 2023/24, against 233 GW in 2019/20, and that the queue held far more generation than needed, with hundreds of gigawatts unlikely ever to connect.

What does "flexibility" mean for a data centre?

Using less power, or using it at a different time or place, when the grid needs it. A few terms come up again and again:

  • Demand response: a customer reduces or shifts its demand when asked, usually for payment or in return for a faster or cheaper connection.
  • Curtailment: reducing output or demand below what was requested. It has two meanings in energy: a grid curtailing a wind farm because it cannot take its power, and a grid curtailing a load such as a data centre. This article mostly means the second.
  • Flexible or non-firm connection: a grid connection that guarantees only part of the requested capacity at all times, with the rest available except when the network is constrained.
  • Load shedding: the grid operator's last resort in an emergency, cutting off demand to stop the whole system failing.

The IEA's 2025 report names operating data centre servers, or their on-site generation and storage, "more flexibly" as one of the main ways to reduce the risks of data centre growth, and adds that "these strategies are still underexplored".

Which AI work can shift, and which can't?

Work that does not have a person waiting for the answer can usually move; work that does, usually cannot. The dividing line is latency: how quickly a result is needed.

Workload Can it shift in time? Can it shift in place? Notes
Training and fine-tuning Often, if jobs save checkpoints Sometimes Long jobs can slow or pause for hours; moving them means moving data
Batch inference (classifying documents, overnight reports, evaluation runs) Usually Usually Deadlines are in hours or days, not seconds
Media processing, re-indexing, backups Usually Often Google's first location-shifting work, in 2021, was video and photo processing
Interactive inference (chatbots, search, coding assistants) Rarely Partly, between nearby regions Users notice delays; capacity must be there at peak
Safety-critical services (health, emergency) No No Reliability comes first

The authors of the Phoenix field trial described below note that "not all AI workloads are temporally flexible", and their trial left real-time inference and model serving untouched. Google, too, says reliability limits apply because services such as Search and Maps, and cloud customers in sectors such as healthcare, need high reliability.

For practical ways to run flexible work on spare capacity, see how to run AI jobs on spare cloud capacity and how to schedule training when the grid is greener.

Is data-centre demand response happening yet?

Yes, in early agreements and trials, mostly in the US so far. The published examples are few, and most of the detail comes from the companies involved.

  • Google and US utilities. In August 2025 Google announced demand response agreements with Indiana Michigan Power and the Tennessee Valley Authority, the first in which it targets machine learning workloads. It said it had already reduced machine learning power demand during three grid events with Omaha Public Power District the previous year, and had worked with Centrica Energy and Elia in Belgium and with Taiwan Power Company on shifting non-urgent computing during grid strain. In March 2026 Google said it had built a total of 1 GW of demand response capacity into long-term contracts with US utilities, adding Entergy Arkansas, Minnesota Power and DTE Energy. Google describes data centre flexibility as "still in the early stages".
  • A field trial in Phoenix. A 2025 paper by Colangelo and colleagues reports a trial on a 256-GPU cluster in a commercial cloud data centre in Phoenix, Arizona, run with Oracle Cloud Infrastructure, NVIDIA and the utility Salt River Project through EPRI's DCFlex initiative. Software slowed and paused flexible training and fine-tuning jobs to achieve a 25% cut in cluster power for three hours during peak grid events, ramping down and up over 15 minutes, with the authors reporting no breaches of agreed service levels. It was one cluster, not a whole site.
  • EPRI's DCFlex. The Electric Power Research Institute (EPRI), a US non-profit research body, launched its Data Center Flexible Load Initiative in late 2024. It aims to set up five to ten large-scale "flexibility hubs" to demonstrate how data centres can support the grid.
  • Batteries in Ireland. In 2022 Microsoft said the uninterruptible power supply (UPS) batteries at its Dublin data centre had been certified, tested and approved to connect to the grid, so they could provide grid services through EirGrid's market via the aggregator Enel X. The announcement described a planned deployment, not results.

How much could flexibility help?

On paper, a lot: modest, occasional curtailment could let grids connect far more new load before they need to expand. The best-known estimate is Rethinking Load Growth (2025), by Tyler Norris and colleagues at Duke University's Nicholas Institute. Looking at 22 of the largest US balancing authorities, serving 95% of US peak load, it estimated how much new load the existing system could take if that load could be curtailed now and then.

Average annual curtailment of the new load New load that could be added (US)
0.25% of maximum uptime 76 GW, equivalent to 10% of US peak demand
0.5% 98 GW
1.0% 126 GW

The authors found the average curtailment event lasted about two hours, and that in nearly 90% of the hours when cuts were needed, at least half of the new load could keep running. They call these "first order" estimates and say follow-up studies are needed to work out the real generation and transmission requirements.

There is a catch the IEA points out: an AI-focused data centre is 10 times more capital-intensive than an aluminium smelter, so curtailing it is very costly. But, it adds, many data centres run with a buffer of spare server capacity, and regulators could encourage operators to use that buffer, or their backup generation and storage, more flexibly.

What are flexible connections and curtailment agreements?

They trade a guarantee of full power at all times for a faster or cheaper connection. The IEA's 2026 report suggests system operators "can explore non-firm grid connections" and reward data centre developers who offer demand response with faster connections. Several jurisdictions now have rules:

  • European Union. Directive (EU) 2024/1711, adopted on 13 June 2024, requires each member state's regulator (or another competent authority) to develop a framework for network operators to offer flexible connection agreements in areas with limited or no network capacity. Flexible connections should not, as a general rule, delay network reinforcement, should convert to firm connections once the network is built, and may become permanent where building the network is not the most efficient answer. Member states had to transpose this by 17 January 2025.
  • Ireland. The Commission for Regulation of Utilities (CRU) decided on 12 December 2025 that new data centres of 10 MVA or more must provide dispatchable on-site or nearby generation or storage that matches their maximum import capacity and takes part in the electricity market. There is no general extra flexibility requirement, but system operators can require demand flexibility case by case. The decision lists early flexible arrangements already in use: EirGrid's Flexible Demand Operating Protocol, which lets it instruct some data centres to lower consumption after other actions are exhausted, and ESB Networks pilots for timed and flexible demand connections. The CRU calls these "still at an early stage and … limited in scale".
  • Great Britain. Ofgem's April 2025 reform replaced "first come, first served" with a queue that favours projects that are "ready" and "needed"; demand-only projects are automatically treated as needed. Its December 2025 consultation on the next stage proposes that customers should be able to choose a firm or non-firm connection with clear terms, while warning that flexibility should not substitute for necessary network investment.

What happens in a grid emergency?

Large loads are increasingly written into emergency rules, so that they can be cut in a controlled way before households. Two examples:

  • Texas. Senate Bill 6, signed and in force from 20 June 2025, sets interconnection standards for loads of 75 MW or more (lower if the regulator decides), with a study fee of at least $100,000. Large loads must disclose on-site backup generation able to serve at least 50% of their demand. In an energy emergency, after using all other market services except frequency response, ERCOT, the Texas grid operator, may have such customers switch to backup generation or curtail load. Transmission-voltage loads connected after 31 December 2025 must have the equipment to be curtailed during firm load shed. The law also creates a competitively procured service for loads of at least 75 MW to reduce demand in emergencies, with at least 24 hours' notice. It says it does not authorise breaking emissions limits.
  • Ireland. The CRU describes mandatory demand curtailment terms under which, in a system emergency, a large user can be told to reduce or remove its demand and is prioritised for disconnection over other customers where at least 60 minutes' notice can be given. New data centres that provide the generation required by its 2025 decision are exempt, but all demand remains subject to emergency load shedding.

What about batteries and backup generators?

Batteries can help the grid with little local pollution; diesel generators can too, but at a cost to air quality. Every large data centre has backup power. The IEA's 2026 report estimates that around 20–25 GW of battery storage could be installed in data centres worldwide by 2030, and that 15–27 GW of on-site gas could power data centres by 2030, mostly in the US. It also notes that AI training and use cause large, rapid swings in power, which on-site storage can smooth.

Many backup generators burn diesel. Microsoft wrote in 2021 that each of its generators runs "no more than a few hours a year or less", mainly for maintenance or outages, and set a goal to end its dependence on diesel for backup power by 2030. Asking generators to run whenever the grid is tight changes that picture. A 2026 report from Virginia Commonwealth University's Institute for Sustainable Energy and Environment found that, near some clusters in Northern Virginia, cumulative exposure to data centre generator emissions was already comparable to, and sometimes above, exposure from a nearby power station, and that if the generators ran to their permitted limits their total potential pollution would far exceed any other polluting facility in the region.

So grid support from backup power is best done with batteries or cleaner generation, and rules that call on backup generators, like Texas's, need to sit alongside air-quality limits.

How should an organisation schedule flexible AI work?

Write down when flexible jobs may run, what the scheduler optimises for, and what deadlines it must keep. Most organisations will not sign a demand response contract, but they do control when their own training, batch inference, backups and re-indexing run, and they can ask their cloud provider for the same.

A scheduling policy should cover:

  1. Which jobs are flexible. List them, with each job's deadline and quality-of-service limit, for example "must finish within 24 hours" or "may pause for up to four hours". Interactive services are out of scope.
  2. What it optimises. Carbon-aware computing runs jobs when grid carbon intensity is lowest. Grid-aware (or demand-aware) scheduling avoids the grid's peak hours and local constraints. They often coincide, but not always: on a windy winter evening, power can be relatively clean while demand is at its peak. Great Britain's Demand Flexibility Service, for example, was set up to reduce demand at evening peaks. The policy should say which signal comes first, and what to do when they conflict.
  3. How it decides. Name the data source and the rule, for example "start batch jobs in the cleanest window in the next 24 hours, unless the grid operator has issued a demand-reduction call".
  4. Location. Whether jobs may move between regions, within data-protection and residency rules.
  5. Review. Report what share of flexible work actually moved, and revisit yearly.

Data sources and tools include:

  • Great Britain's Carbon Intensity API, run by NESO with Environmental Defense Fund Europe, the University of Oxford and WWF, which forecasts carbon intensity more than 96 hours ahead for 14 regions at 30-minute resolution (CC BY 4.0 licence).
  • WattTime, which publishes a marginal emissions signal (the emissions of the power plants that respond to a change in demand) at five-minute resolution, with a 72-hour forecast.
  • Electricity Maps, whose hourly grid mix and carbon intensity data Google Cloud uses for its regional figures.
  • Cloud providers' regional data. Google Cloud publishes an hourly-based carbon-free energy percentage and grid carbon intensity for each region, marks regions with at least 75% carbon-free energy as "Low CO2", advises running batch jobs in the cleanest region, and lets organisations restrict resources to low-carbon regions by policy.

Few public tools publish a "grid stress" signal for businesses, so grid-aware scheduling usually relies on operator alerts, tariffs or a flexibility provider. See how to find grid carbon intensity data, how to pick a low-carbon cloud region and how to write a green AI policy.

What can public policy do to make flexibility normal?

Pay for flexibility, price electricity by time, and build flexibility into connection terms.

  • Prices that vary by time. Directive (EU) 2024/1711 requires member states to let customers with a smart meter ask for a dynamic electricity price contract, which passes on prices that change through the day. Prices like this give large users a reason to move flexible work out of peaks.
  • Paid flexibility schemes. Great Britain's Demand Flexibility Service, run by NESO, rewards homes and businesses, through suppliers and aggregators, to shift when they use electricity. It became year-round in November 2024. Ofgem approved a new design on 25 March 2026, which cut the minimum size from 1 MW to 0.1 MW, pays for increasing use as well as reducing it, and is open to industrial and commercial users; NESO's page says it will also be used for local constraint management from 7 October 2026. NESO does not single out data centres as participants.
  • Connection terms. The examples above, from Texas's emergency rules to Ireland's generation requirement and the EU's flexible connection framework, show the choice: require flexibility as a condition of connecting, or offer faster connections in return for it.
  • Queue reform. The IEA recommends reforming how data centre connection queues are managed and streamlining permitting.

Policymakers should weigh who carries the risk: a flexible connection only helps if the curtailment it allows is clear, measured and enforced. See the policy guide and how to encourage greener AI as a policymaker.

What does this mean for AI users and buyers?

Ask providers whether, and how, their data centres work with the grid, and make your own flexible work easy to move. Useful questions for a cloud or AI provider:

  • Do any of your sites take part in demand response or hold flexible connections? Since when, and how much capacity?
  • Can we mark jobs as flexible, with a deadline, so you can move them in time or place?
  • What backs up your sites, and how often did the backup generators run last year, other than for testing?
  • Do you schedule your own batch work against carbon intensity, grid peaks or both?

Grid connection is not the only way a site affects its area: for whether its waste heat can warm nearby buildings, see data centre waste heat. For siting and efficiency questions, see green AI hosting and data centres.

What are the limits and open questions?

Flexibility is promising but little-tested at scale, and most evidence comes from the companies involved.

  • Scale. The Phoenix trial covered one cluster; Google gives a total capacity but not how often it has been called or how much was delivered.
  • Models, not measurements. The Duke figures are first-order estimates for the US that rest on simplifying assumptions; other grids will differ.
  • Cost and incentives. AI hardware is expensive, so operators will want payment, faster connections or both. Service agreements would also need to change before customers widely opt in to flexibility tiers, as the Phoenix authors note.
  • Backup trade-offs. Flexibility that relies on diesel generators shifts the burden onto local air quality.
  • Verification. Little public data shows how much flexibility operators have actually delivered, or how often their backup generators ran.
  • Rebound. Flexibility that lets more data centres connect sooner can also mean more total electricity use; see efficiency is not sufficiency.

What to do next

  • Read the IEA's Energy and AI reports for the grid picture, and your grid operator's connection and flexibility pages for local rules.
  • List your organisation's flexible AI jobs, give each a deadline, and add a scheduling rule to your green AI policy.
  • Move flexible jobs to cleaner hours and regions: see how to run AI jobs on spare cloud capacity.
  • Ask your AI and cloud providers the questions above, and put them in contracts: see sustainable AI procurement.
  • If a data centre is planned near you, ask about its grid connection terms and backup power: see how to have a say on a data centre near me.
  • If you make policy, look at flexible connections, time-varying prices and emergency rules together: see the policy guide.

Frequently asked questions

Can AI data centres reduce their power use when the grid is stressed?

Some of it. In a 2025 field trial in Phoenix, Arizona, a 256-GPU AI cluster cut its power use by 25% for three hours during peak grid events by slowing and pausing flexible jobs. Training and batch jobs can usually wait; live services that answer users cannot.

What is a flexible or non-firm grid connection?

A connection where the customer can draw its full capacity most of the time but agrees to reduce demand when the network is constrained, often in return for connecting sooner. EU law since 2024 requires a framework for such agreements in areas with limited network capacity.

Can grid operators switch off data centres in an emergency?

In some places, yes, under set rules. Texas's 2025 law (SB 6) requires transmission-voltage loads connected after 2025 to have equipment that lets them be curtailed during firm load shed, and Ireland's regulator describes data centres on mandatory demand curtailment terms being prioritised for disconnection with at least 60 minutes' notice.

What is the difference between carbon-aware and grid-aware scheduling?

Carbon-aware scheduling runs flexible work when electricity is cleanest; grid-aware scheduling avoids times when the grid is at peak or a local network is constrained. They often coincide, but a windy evening can be both clean and at peak demand, so a policy needs to say which comes first.

Are data centre backup generators a problem?

They can be. Many burn diesel and normally run only for tests and outages, but running them more often to support the grid trades grid relief for local air pollution and emissions. A 2026 Virginia Commonwealth University report found exposure near some data centre clusters already comparable to a nearby power station.

Sources

  1. Energy and AI: executive summary, International Energy Agency (2025)
  2. Key questions on energy and AI, International Energy Agency (2026)
  3. Data centres metered electricity consumption 2025: key findings, Central Statistics Office, Ireland (2026)
  4. Large Energy User connection policy decision paper (CRU2025236), Commission for Regulation of Utilities, Ireland (2025)
  5. Summary decision document: TMO4+ connections reform proposals (code modifications, methodologies and impact assessment), Ofgem (2025)
  6. Connections end-to-end review: updated proposals and next steps, Ofgem (2025)
  7. Directive (EU) 2024/1711 amending Directives (EU) 2018/2001 and (EU) 2019/944 as regards improving the Union's electricity market design, European Union (2024)
  8. Senate Bill 6, 89th Legislature (enrolled text), Texas Legislature (2025)
  9. Bill history: SB 6, 89th Legislature, Regular Session, Texas Legislature Online (2025)
  10. Testimony of Tyler H. Norris on Rethinking Load Growth (Norris, Profeta, Patino-Echeverri and Cowie-Haskell, Nicholas Institute, Duke University, 2025), US House Energy and Commerce Committee (2025)
  11. How we're making data centers more flexible to benefit power grids, Google (2025)
  12. A new milestone for smart, affordable electricity growth, Google (2026)
  13. We now do more computing where there's cleaner energy, Google (2021)
  14. Carbon free energy for Google Cloud regions, Google Cloud (2026)
  15. DCFlex: Data Center Flexible Load Initiative (supplemental project notice 3002031004), Electric Power Research Institute (2025)
  16. Turning AI data centers into grid-interactive assets: results from a field demonstration in Phoenix, Arizona, Colangelo et al. (2025)
  17. Microsoft datacenter batteries to support growth of renewables on the power grid, Microsoft (2022)
  18. Progress on our commitment to sustainable backup power in datacenters by 2030, Microsoft Azure (2021)
  19. Localized air pollution impacts from data centers in Northern Virginia, Pitt, Suen and Plisko, VCU Institute for Sustainable Energy and Environment (2026)
  20. Demand Flexibility Service (DFS), National Energy System Operator (NESO) (2026)
  21. NESO announces shake-up to new look Demand Flexibility Service, National Energy System Operator (NESO) (2026)
  22. Carbon Intensity API, NESO, Environmental Defense Fund Europe, University of Oxford and WWF (2026)
  23. Marginal CO2 (MOER) data signal, WattTime (2026)